April 2009 The project is placed on hold by DDR.
March 2009 The City has been awaiting submittal of a Design Review application for Phase I of the Totem Lake Mall redevelopment project. Phase I consists of the redevelopment of the Lower Mall and street improvements to 120th Avenue NE. At this time, the City does not know the tenant mix being contemplated by DDR
January 2006 - City Council On January 17, 2006, the City Council approved a development agreement with Coventry /DDR to redevelop Totem Lake Mall by committing $15 million towards the purchase of right-of-way for a new plaza/boulevard, 120th Avenue NE street improvements, and a portion of the parking structure. View the City staff memo. (PDF - 1.7MB). View the redevelopment agreement (PDF 314kb)
November 2005 - Design Review Board (DRB) At their November 7, 2005 meeting, the DRB approved, with conditions, the Conceptual Master Plan for the Totem Lake Mall. View the applicant's conceptual proposal for redeveloping Totem Lake Mall (PDF - 1.9MB).
October 2005 - City Council At their October 18, 2005 meeting, the City Council approved the Memorandum of Understanding (MoU) (with revisions). Approval of the MoU gives direction for the City to move forward in creating a Development Agreement for the redevelopment for the Mall. View the City Staff memo (PDF - 888kb).
September 2005 - City Council At their September 20, 2005 Council meeting, the City Council reviewed the proposed MoU which outlines the general terms of the City's financial participation to the Mall redevelopment project.
Prior to making a decision on the MoU, the City Council requested that City staff provide additional information regarding the economics and legal aspects of the City's participation. The City Council will be revisiting the MoU at their October 18, 2005 meeting. View City Staff memo on MoU. (PDF-490kb)
September 2005 - Design Review Board (DRB) The DRB held the public meeting for the Totem Lake Mall Conceptual Master Plan on September 12, 2005. The Conceptual Master Plan will be the document which will contain the design guidelines on which future development of the Mall will be based.
The DRB provided feedback to the Mall owner on additional changes. The DRB continued the public meeting to the November 7, 2005 DRB regular meeting date. View the draft Conceptual Master Plan.
May 2005 - City Council At the City Council's May 17, 2005 study session, the new Mall owners, DDR, formally presented their proposal for redeveloping Totem Lake Mall to the City Council.
Click here to watch the City Council Meeting May 17, 2005 May 17, 2005, Study Session.
August 2004 - TL2 adopted Zoning for the Totem Lake Mall property was adopted by the City Council on August 3, 2004, Ordinance 3956.
April 2004 - Totem Lake Action Team The new Mall owners, DDR, met with the Totem Lake Action Team to discuss concerns and new opportunities associated with the redevelopment of the Totem Lake Mall.
March 2004 - Design Review Board (DRB) The new owners met with the DRB to preliminarily discuss design concerns with redevelopment of the Mall property. Information from this meeting will be incorporated into a more formal application when the owners decide to apply for the Design Response Conference. This will be a public meeting.
|